MORIS Italy is glad to present the latest evolution of our “threaded joint” for two jacks assembling.

The new joint system guarantees:

• Reduced installation time.

• Improvement of the coupling phase of piston and cylinder parts and better final result.

• New packaging with increased protection for transport and handling on site.

The new junction will be in production as early as next week, starting with the 100 mm diameter pistons, and gradually extending to all our standard production.

The pistons built with the new system will be accompanied by the assembly manual that we are publishing in our website; in case of needs, our technical service is at your disposal.

SEQUENCE OF ASSEMBLY THREADED JUNCTION – REV E